Currently backfilling foundations and prepping for slab pour.
Update on Schedule:
- Foundation , stone under slab are ready for slab pour, now scheduled for next Wednesday or the following Monday depending on weather.
- Roof trusses and lumber have been ordered and released for delivery to ship.